How much does a legal basement apartment cost in Toronto?
A legal basement apartment in Toronto costs $60 to $80 per square foot, and can run higher, according to one Toronto builder's 2026 guide. A basic finish with no suite costs $25 to $35 from the same builder. Lowering the floor for headroom, a separate entrance and sound control between units move the price most.
By the CostGuide.ca editorial team. Published 18 November 2026. Prices checked November 2026. The ranges are published prices from 2 contractors and suppliers, not averages. Each row names its source.
Get a quote from a local builder
What does a Toronto builder charge to finish a basement or build a suite?
One Toronto builder prices a legal secondary suite at $60 to $80 per square foot, against $40 to $55 for a mid-range basement with a bathroom and no suite.
Toronto basement apartment, finishing and underpinning prices
Low to high range
| Job | Low | High |
|---|---|---|
| Legal secondary suite (basement apartment conversion)$60 to $80per sq ft, one contractor's published price [1]One Toronto builder; can run higher | $60 | $80 |
| Basement finishing, mid-range with bathroom (no suite)$40 to $55per sq ft, one contractor's published price [1]One Toronto builder | $40 | $55 |
| Basement finishing, basic (no suite)$25 to $35per sq ft, one contractor's published price [1]One Toronto builder | $25 | $35 |
| Basic finish, 1,000 sq ft basement (no suite)$25,000 to $35,000per basement, one contractor's published price [1]One Toronto builder | $25,000 | $35,000 |
| Basement lowering$80 to $120per sq ft, one contractor's published price [2]From a Toronto underpinning contractor | $80 | $120 |
| Underpinning, per linear foot of foundation$300 to $480per linear foot, one contractor's published price [2]From a Toronto underpinning contractor | $300 | $480 |
| Engineering for underpinning$2,000 to $5,000per project, one contractor's published price [2]From a Toronto underpinning contractor | $2,000 | $5,000 |
Prices in CAD as local contractors publish them. Most do not say whether 13% HST is included, so ask for HST as its own line. Checked November 2026.
The finishing and suite rows come from one Toronto renovation builder's 2026 guide. The lowering, underpinning and engineering rows come from a separate Toronto underpinning contractor. We found several other Toronto suite guides but left out any we could not tie to a street address, a licence or a named owner with working contact details, so read these as two local firms' figures and get quotes of your own.
None of the Toronto figures says whether HST is included. No single source here prices a suite and headroom work together, so if your basement needs lowering, ask each builder how the two jobs are split on the quote. For the same Ontario rules with a different builder's numbers, see the Ottawa basement apartment guide, or compare five cities in the Canada basement suite cost guide.
Want a real number for your basement suite?
What do the entrance, kitchen and other parts add in Toronto?
A separate entrance dug below grade is the largest single add-on at $15,000 to $25,000, while a 3-piece bathroom adds $12,000 to $20,000 and a suite kitchen $10,000 to $20,000, by one Toronto builder's count.
Toronto basement apartment add-ons
Low to high range
| Job | Low | High |
|---|---|---|
| Separate basement entrance (excavation, stairs, door)$15,000 to $25,000per entrance, one contractor's published price [1]Below grade entry with digging | $15,000 | $25,000 |
| Add a 3-piece bathroom to a basement project$12,000 to $20,000per bathroom, one contractor's published price [1]Quoted for a 1,000 sq ft basement project | $12,000 | $20,000 |
| Kitchenette or full kitchen for a suite$10,000 to $20,000per suite, one contractor's published price [1] | $10,000 | $20,000 |
| Soundproofing between units (resilient channel and mineral wool)$5,000 to $10,000per suite, one contractor's published price [1] | $5,000 | $10,000 |
| Engineering and architectural drawings for a secondary suite$3,500 to $8,000per project, one contractor's published price [1] | $3,500 | $8,000 |
| Egress window installation$3,500 to $7,000per window, one contractor's published price [1]The same page also gives 5,000 to 7,000 in its calculator | $3,500 | $7,000 |
Prices in CAD as local contractors publish them. Most do not say whether 13% HST is included, so ask for HST as its own line. Checked November 2026.
Why does one Toronto basement apartment cost more than another?
Headroom work, the kind of entrance, sound control between units and the drawings a permit needs decide most of the gap between two Toronto quotes.
- Lowering the floor. Where a basement is too low for a suite, lowering it costs $80 to $120 per square foot, a Toronto underpinning contractor reports. Underpinning the walls is priced by length, at $300 to $480 per linear foot of foundation. [2]
- An engineer on underpinning. The same contractor puts engineering at $2,000 to $5,000. The City requires a Professional Engineer's testing and reports at the first and last stages of all underpinning work, so this is not optional. [2] [4]
- The entrance. A below-grade entrance with excavation, stairs and a door runs $15,000 to $25,000. The City treats basement entrances under its underpinning permit guide, so expect a permit for this part too. [1] [4]
- Sound between units. Resilient channel and mineral wool between the suite and the home above add $5,000 to $10,000, the Toronto builder says. [1]
- Drawings. Engineering and architectural drawings for a secondary suite cost $3,500 to $8,000. Ask whether a builder includes them or bills them on their own. [1]
- Egress windows. Each egress window costs $3,500 to $7,000, though the builder's own calculator shows a narrower, higher band, so ask for a fixed price per window. Our egress window guide for Calgary explains how the foundation type changes the job. [1]
What rules and programs apply to a Toronto basement apartment?
Toronto needs a building permit for a secondary suite and for underpinning, Ontario bars development charges on many second units, and the City's flood subsidy helps pay for backwater valves and sump pumps.
What does a Toronto building permit for a basement apartment cost?
A secondary suite needs a City of Toronto building permit. From January 1, 2026 the fee is $11.53 per square metre of interior alteration plus a $56.33 residential unit fee for each new unit (as at November 2026). The City defines a secondary suite as a unit smaller than the main one, inside an existing detached house, semi-detached house or townhouse, and names a basement apartment as the common example. [3]
Does underpinning a Toronto basement need a permit and an engineer?
Yes. Underpinning a foundation, the work used to lower a basement floor or add a below-grade entrance, needs a building permit, with a 2026 fee of $12.37 per linear metre, and a Professional Engineer must provide testing and reports at the first and last stages (as at November 2026). Where the new foundation goes below a neighbouring building's footing, an engineer must design it and review it on site. Extra engineer commitment forms apply above 1,200 mm of unsupported height or in clay or silt soil. [4]
Will Toronto help pay for flood protection in a basement suite?
Yes. Toronto's Basement Flooding Protection Subsidy pays up to 80% of the invoice, within set caps, to a total of $6,650 per property, for work done on or after November 12, 2025 (as at November 2026). The caps are $500 for a plumbing assessment, $1,600 per backwater valve and alarm (up to two), $2,250 for a sump pump and alarm, $300 for a battery backup and $400 for weeping tile severance and capping. The contractor must hold a City of Toronto business licence, and funding is first come, first served. [5]
Are development charges owed on a Toronto basement apartment?
Usually not. Under the rules set out in Ontario's January 2023 decision, municipalities cannot charge development charges, whatever the unit size, on certain second and third units, or requiring parkland or cash in lieu for them (as at January 2023). The same decision allows up to three units per lot in many serviced residential areas. Confirm with the City that your property qualifies before you budget without them. [6]
Is there a federal loan for building a Toronto basement suite?
No. The Canada Secondary Suite Loan announced in December 2024 never launched, and CMHC's 2026 to 2030 plan summary says it will not be implemented (as at November 2026). CMHC does insure refinancing to add a suite: up to 90% of the lending value (the lower of the as-improved value or the current value plus the cost of the work), for up to 4 units, with up to 30 years of amortization and an as-improved value under $2,000,000. Ask your lender about it. [7] [8] [9]
What should a Toronto basement apartment quote include?
A Toronto quote should name who handles the permit, drawings and engineering, and price the entrance, any underpinning, sound control and each egress window as separate lines.
- Who applies for the building permit, and whether the City fee is in the price
- Drawings and engineering, included or billed separately
- How the suite gets its own entrance, and whether digging is included
- Any underpinning or lowering, priced per linear foot or per square foot, with the engineer named
- Soundproofing between the units as its own line
- A price for each egress window, including the well
- How changes and extra work are priced
- HST as a separate line, not folded into the total
Basement apartment terms on a Toronto quote
- Underpinning
- Digging below the existing footings and building new foundation under them so the basement floor can go lower. Toronto requires a permit and engineer reports for it. [4]
- Secondary suite
- The City of Toronto's term for a second, smaller unit in an existing detached house, semi-detached house or townhouse. [3]
- HST
- Harmonized sales tax. Ontario's rate is 13%, according to the Canada Revenue Agency (as at November 2026). Ask for it as its own line on every quote. [10]
- Resilient channel
- A metal strip fixed between the framing and the drywall to cut sound passing between units. One Toronto builder prices it with mineral wool as its soundproofing line. [1]
Toronto basement apartment questions
How much does it cost to finish a 1,000 sq ft basement in Toronto?
A basic finish on a 1,000 sq ft Toronto basement costs $25,000 to $35,000 with no suite, according to one Toronto builder. The same builder puts a mid-range basement with a bathroom at $40 to $55 per square foot, and a legal suite at $60 to $80 per square foot or more.
What does a separate entrance to a Toronto basement cost?
A separate entrance with excavation, stairs and a door costs $15,000 to $25,000, one Toronto builder reports. A new below-grade entrance comes under the City's underpinning and basement entrance permit, so budget for the permit and an engineer as well as the construction.
How much does underpinning a Toronto basement cost?
A Toronto underpinning contractor prices underpinning at $300 to $480 per linear foot of foundation and lowering at $80 to $120 per square foot, with engineering adding $2,000 to $5,000. The City's permit fee is charged per linear metre on top of that.
How much is an egress window for a Toronto basement bedroom?
One Toronto builder prices an egress window at $3,500 to $7,000 each, though another part of its own page gives a narrower, higher band. Ask for a fixed price per window that names the digging, the well and the cut through the foundation wall.
Do Toronto basement apartment prices include HST?
None of the builder or underpinning rates on this page says whether HST is included. Ask every builder to show HST as its own line, and to say whether permits, drawings and engineering sit inside the price or come on top, so you compare the same work.
Sources
- Basement Renovation Cost Toronto (2026), TopDown Renovations (1300 Yonge St, Toronto, ON M4T 1X3; phone (647) 250-9808). Checked 2026-11-18.
- TRUE Basement Underpinning Cost in Toronto + Calculator 2026, Strong Basements Inc. (2275 Lake Shore Blvd W, Unit 222, Etobicoke, ON). Published 2026-09-27. Checked 2026-11-18.
- Secondary Suites (building permit application guide), City of Toronto. Published 2026-11-03. Checked 2026-11-18.
- Residential Underpinning (including Basement Entrances), City of Toronto. Published 2026-08-18. Checked 2026-11-18.
- Basement Flooding Protection Subsidy Program, City of Toronto. Published 2026-11-06. Checked 2026-11-18.
- Proposed Changes to Ontario Regulation 299/19: Additional Residential Units (ERO 019-6197, decision), Government of Ontario, Ministry of Municipal Affairs and Housing (Environmental Registry of Ontario). Published 2023-01-06. Checked 2026-11-18.
- 2024 Fall Economic Statement: Making it easier for homeowners to build secondary suites, Department of Finance Canada. Published 2024-12-10. Checked 2026-11-18.
- Summary of the 2026-2030 Corporate Plan, Canada Mortgage and Housing Corporation. Checked 2026-11-18.
- CMHC Refinance for Building Secondary Suites, Canada Mortgage and Housing Corporation. Checked 2026-11-18.
- GST/HST calculator (and rates), Canada Revenue Agency. Checked 2026-10-29.